Project

The course project is divided into six deliverables and will count towards 70% of your final grade.
Deliverables
No.Title Assigned Due ByTesting/Turnin Code to Download % of Grade
1Heap file implementation Jan 15 Jan 25a1test.tar.gz Chris.tar 10%
2Sorted file implementation Jan 29 Feb 12; Feb 23a2test.tar.gz
a2-2test.tar.gz
Pipe.tar 20%
3Relational Operations March 3 March 21a3test.tar.gz Function.tar 10%
4Query Compiler (1) March 27 April 7a4-1test.tar.gz NA 7.5%
 Query Compiler (2) April 14 April 25TBA Parser.tar 7.5%
5Final Project April 27 Demo timedemo.tar.gz NA 15%

Several groups have volunteered a copy of their A2-2 code.  If you are unsure as the to the stability of your own code, are free to use one of these codes as a basis for A3 and beyond. Many thanks to those who donated!